District heating

Narbonne

With this new solar thermal plant for newHeat, Savosolar add a new leading reference in the French market of solar district heating. This approximately 3,000 m2 solar thermal field (aperture), will allow to replace 2,410 MWh of former gas heated heat by renewable heat on Narbonne’s city network, manage by a subsidary of Dalkia.

Savosolar, on the behalf of newHeat, built mainly the whole solar plant, from the solar collector’s field until the outlet of the heat exchanger to the storage thermal tank, ie: solar field, piping and solar station. More then 200 of our Savo 15 SG-M collectors, ensuring a high energy yield while reducing 510 tons of CO2 emissions per year from the district heating system of the city. The production of solar field during winter will even allow an increasing of the yield of the existing biomass boiler.

Location

France

Construction status

Finished

Installation year

2021

Solution type

District heating

Number of collectors

202

Collector Area

2996 m2
, gross

Collector Type

Savo 15 SG M

Power

24500 kW

Energy production

2410
MWh/a

La Caridad

Savosolar and its partner Jorgensen have been selected by Grupo Mexico for the implementation of their first solar thermal plant to deliver carbon free heat to their mining process. In this very energy efficient mining process, only 62 pieces of Savo 15SGM large scale high performance flat plate collectors are sufficient deliver 1,2 GWh of energy over the year and cover 100% of the production need during most of the sunny season.

Fernwärme Ettenheim

As a general contractor, Savosolar built a solar thermal system on behalf of Fernwärme Ettenheim GmbH for the largest possible solar feed-in into the existing district heating network. 112 pieces Savo 15 SG-M large collectors generate fuel-free healthy heat, which is temporarily stored in two 100 m³ buffer storage tanks.
This also allows the operating hours of the CHP and the biomass boiler to be optimized. The scope of delivery included the fence and video surveillance system, as well as the creation of a meager meadow to enrich local biodiversity.

The construction work was temporarily interrupted due to the COVID19 restrictions. All system hydraulics were completely housed in a container. The keys were handed over in October 2020.

A PV system still to be built on the east side will generate the electricity for the pumps in the future.

The picture on the left shows the boiler house and the buffer storage tank. Handover of keys from Jari Varjotie, CEO Savosolar Oyj, to Peter Blaser, managing director of the customer.

Løgumkloster Fjernvarme

Løgumkloster Fjernvarme is a district heating company which annually supplies 35,000 MWh of heat to over 1,500 customers. Heat is produced with a hybrid heating system consisting of a 3 MW pellet boiler, a 1.3 MW hybrid heatpump, a 3 MW absorption heat pump and a solar collector field of 15,300 m2. Additionally, the plant has two gas engines which are capable of producing 7.6 MW of heat and 6 MW of electricity and a 10 MW gas boiler which acts as back-up.

In 2015, Savosolar delivered a 9,700 m2 solar thermal field to Løgumkloster. The second order of 5,600 m2 was delivered and commissioned in the beginning of 2016. The complete field consists of 1030 Savo 15 SG collectors and covers about 20% of the annual thermal energy need of the district heating network. The largest part of the heat demand is covered by the pellet boiler, but Løgumkloster Fjernvarme has plans to change this in the future by extending the solar field and building a large seasonal water storage.