District heating

Oulun Seudun Sähkö

Savosolar delivered -once again- the largest solar thermal installation in Finland. This system is located way North in Tupos, Liminka - less than 200 km from the Arctic Circle.

The heating load of Tupos district heating is usually covered by wood pellets. Yet during summer time, the load is often so low, that the substantial wood pellet burner cannot be properly used and an oil burner got used, instead. The special challenge here has been to design a very efficient solar thermal system that could replace the oil consumption in summer to run the district heating network almost completely fossil-free.

Location

Finland

Construction status

Finished

Installation year

2018

Solution type

District heating

Number of collectors

Collector Area

356 m2
, gross

Collector Type

Savo 15 SG

Power

249 kW

Energy production

Fernwärme Ettenheim

As a general contractor, Savosolar built a solar thermal system on behalf of Fernwärme Ettenheim GmbH for the largest possible solar feed-in into the existing district heating network. 112 pieces Savo 15 SG-M large collectors generate fuel-free healthy heat, which is temporarily stored in two 100 m³ buffer storage tanks.
This also allows the operating hours of the CHP and the biomass boiler to be optimized. The scope of delivery included the fence and video surveillance system, as well as the creation of a meager meadow to enrich local biodiversity.

The construction work was temporarily interrupted due to the COVID19 restrictions. All system hydraulics were completely housed in a container. The keys were handed over in October 2020.

A PV system still to be built on the east side will generate the electricity for the pumps in the future.

The picture on the left shows the boiler house and the buffer storage tank. Handover of keys from Jari Varjotie, CEO Savosolar Oyj, to Peter Blaser, managing director of the customer.

La Caridad

Savosolar and its partner Jorgensen have been selected by Grupo Mexico for the implementation of their first solar thermal plant to deliver carbon free heat to their mining process. In this very energy efficient mining process, only 62 pieces of Savo 15SGM large scale high performance flat plate collectors are sufficient deliver 1,2 GWh of energy over the year and cover 100% of the production need during most of the sunny season.

Kherson

Savosolar’s first commercial solar cooling system was delivered to a school in Ukraine. The entire school was pre-fabricated in Finland and delivered to Ukraine by Elemenco Oy.

Outside of the cooling period, the solar thermal system produces energy for domestic hot water and space heating needs. During the hot summer time, three adsorption chillers cool the building via the air handling unit. The adsorption chillers, which were delivered by Savosolar, are driven by the solar thermal system.